| April - June |
2007 |
Initial Public Outreach Completed |
| June |
2007 |
Approval of Draft Master Plan |
| June |
2007 |
Adopt Affirmative Action/Economic Inclusion Plan with MWBE/EEO Goals |
| July |
2007 |
RFP's For Designer, CM and Operator |
| September |
2007 |
DGEIS Available for Public Comment |
| Sept./Oct. |
2007 |
Designer, CM and Operator Under Contract |
| Nov./Dec. |
2007 |
Draft Cost Estimate Completed |
| Nov./Dec. |
2007 |
Draft Financing Plan Completed |
| December |
2007 |
ACCA Preliminary Study of the Authority to be Submitted to State, Albany County, and City of Albany |
| January |
2008
2008
2008 |
GEIS Process Completed
Property Acquisition
Groundbreaking |
| last Quarter |
2010 |
Opening |